Search our Site
|
Segment 2
===================== SEGMENT NUMBER: 2 Proposed: _______ Existing: ___x___ APPROXIMATE LENGTH: .4 miles SEGMENT ENDPOINTS: START: River Mountains Trail trailhead parking lot off of US 93 just
southwest of Hemenway Park FINISH: Industrial Road at US 93 SEGMENT NARRATIVE. This is a 12-foot asphalt multi-use trail that is part of the Boulder
City bike path and trail system. The trail runs parallel to US 93 and
generally follows an uphill grade to Industrial Road. EXISTING AUTHORIZED USES (S): __x__ hiking __x__ mountain bicycling __x__ road bicycling _____ horseback riding __x__ other (walking, jogging, rollerblading) EXISTING TRAIL CONDITIONS: TRAIL WIDTH: 12 feet TRAIL TREAD/SURFACE. Asphalt OTHER FEATURES: Minor separation from edge of US 93. No landscaping. LAND OWNERSHIP AND OTHERS WITH EASEMENTS OR OTHER LEGAL ACCESS: Boulder City holds ownership and easements for trail use. The trail lies
within US 93(NDOT) right-of-way. LEAD TRAIL PLANNING, DEVELOPMENT AND MANAGEMENT ENTITY: Boulder City PROPOSED OR PENDING LAND USE CHANGES/OR OTHER OPPORTUNITIES OR OBSTACLES: None known. TRAIL DEVELOPMENT OVERVIEW SUMMARY: This is an existing trail segment. This segment was
completed in late summer 1997. It is a 12-foot wide asphalt multi-use trail
without equestrian access. This segment is not proposed to have a gravel
component for equestrian or mountain bike use at this time. Should the city
desire a companion gravel corridor, it could be added. To Segment 1 To Segments 3 and 4
Remember desert tortoises and big horn sheep have the
"right-of-way" and are not to be disturbed
|
Send mail to
|